Tata Power beat analyst estimate with a profit of Rs 996 crore in Q4. Going ahead, the integrated power company would be ready with a detailed project report (DPR) for its nuclear projects. Its MD & CEO Praveer Sinha tells Raghavendra Kamath that data centres are not a significant opportunity for power players. Excerpts: Where are you incurring the Rs 25,000-crore capex planned for FY 27 Essentially four buckets,25% will go into large utility scale projects, 25% in transmission projects in Mumbai and others, 25% in T&D (transmission and distribution) put together, and remaining in hydro and pumped storage (PSPs) and project completion.
For suggestions and feedback click here.
Disclaimer: IMC is not responsible for any kind of loss arising due to the information. You are receiving this newsletter because you have subscribed to this service. To unsubscribe click here. Head Office : IMC Bldg., IMC Marg, Churchgate, Mumbai - 400 020 India | Tel : 91-22-71226633 | Fax : 91-22-22048508 / 22838281 E-Mail : imc@imcnet.org | Website : www.imcnet.org