L&T bags Rs 10,000-15,000 crore NTPC order for 1,600 MW thermal power plant in Chhattisgarh
30-Jul-2026

Larsen & Toubro Carbonlite Solutions has bagged an order from NTPC for a Limited Notice to Proceed (LNTP) for a 1,600 MW Thermal Power Plant in Chhattisgarh. The contract falls within the ambit of a mega order valued at 10,000-15,000 crore. L&T: Mega order details Under the scope of work, L&T would work for the main plant package of NTPC. The package is for a 2×800 MW Lara Stage-III thermal power plant in Chhattisgarh, and the notice to proceed will be issued after the project receives environmental clearance and the LNTP is completed.

News Source:- https://www.financialexpress.com/business/industry/lampt-bags-rs-10000-15000-crore-ntpc-order-for-1600-mw-thermal-power-plant-in-chhattisgarhnbsp/4306308/